VerbouwPro
Regulations

Contractor goes bankrupt during the renovation: what now?

8 October 202611 min readVerbouwPro Editorial Team

The building site has gone quiet, nobody answers the phone any more and the insolvency register lists your contractor as bankrupt. What happens now to your contract, to the instalments you have already paid and to the materials lying on your driveway? Step by step: the curator and Article 37 of the Faillissementswet (Dutch Bankruptcy Act), your claim as an unsecured creditor, subcontractors knocking on your door, the guarantee of a quality mark, your insurance, restarting with a new contractor and how to keep this risk small on your next renovation.

A contractor's bankruptcy is the worst-case scenario a renovation can bring for the client: the work has stopped, money has already been paid and the house is half open. Yet it is not a situation without rules. The Faillissementswet (Dutch Bankruptcy Act) determines who now decides on your contract, the Burgerlijk Wetboek (BW, Dutch Civil Code) determines who owns the materials lying on the building site, and quality marks and insurance policies determine whether anyone else bears the extra costs. This article goes through the steps in the order in which they come up in practice. The outcome differs from case to case; where large sums are at stake, legal advice, for example through your legal expenses insurance, is no unnecessary luxury.

Step 1: verify the bankruptcy and stop paying the contractor

Rumours are not a bankruptcy. A company is only bankrupt once the court has declared it so; in the same judgment the court appoints a curator (trustee in bankruptcy) (Article 14 of the Faillissementswet). That ruling is entered in the Centraal Insolventieregister (Central Insolvency Register) of the Dutch judiciary (Article 19 of the Faillissementswet), a public register that you can search online yourself by name, KvK number (Chamber of Commerce registration) or postcode and house number. The bankruptcy is also recorded in the KvK Handelsregister (Trade Register), including the name of the curator. If you look up the contractor and find nothing, there may be a suspension of payments, a debt arrangement or simply a contractor who no longer responds; in that last case the ordinary rules for breach of contract apply, with a formal notice of default as the first step.

Once the bankruptcy has been declared, you pay nothing more to the contractor directly. After the judgment the contractor may no longer dispose of their assets; only the curator has that authority. If you still pay an outstanding instalment into the old account, you run the risk that the payment does not discharge your debt and that the curator claims the amount again. Only pay on the written instruction of the curator, and only for work that has actually been carried out.

Step 2: the curator and your contract (Article 37 of the Faillissementswet)

Your construction contract does not end automatically because of the bankruptcy. The law gives the curator the choice of still performing the contract or not. Because you cannot be left in uncertainty indefinitely, you can force that choice: you give the curator a reasonable deadline in writing to state whether they will perform the contract. If the curator does not declare themselves willing within that deadline, they lose the right to demand performance from you (Article 37(1) of the Faillissementswet). If they do declare themselves willing, they must provide security for that performance (Article 37(2)). In practice, with a private renovation a curator rarely chooses to perform: there are no staff left, no credit with suppliers and no benefit to the estate. So expect to have to carry on yourself.

Send that letter by e-mail and by registered post, state the bankruptcy number, enclose the contract and an overview of the instalments paid, and in the same letter ask the curator for a position on the materials on the building site and for release of the works, so that you can bring in another contractor. If no response comes or the curator refuses, you can terminate the contract; the claim arising from that you submit as an unsecured creditor (Article 37a of the Faillissementswet).

Step 3: your prepaid instalments are an unsecured claim

Everything you have paid for work that was not carried out, together with the extra costs a new contractor charges you, makes up your claim against the estate. You submit it to the curator with supporting evidence: the contract, invoices, proof of payment and preferably a record of the state of the work. Lawyers call this "submitting for verification". Do so quickly and completely; on the basis of all the claims submitted, the curator draws up an order of priority and a distribution list.

Be realistic about what it will yield. First the costs of the estate are paid, including the curator's fee, then the preferential creditors, such as the Belastingdienst (Tax and Customs Administration) and the UWV (Employee Insurance Agency), while a bank with a right of pledge or mortgage recovers from its collateral as a secured creditor outside the order of priority, and only after that the ordinary, unsecured creditors, which is where you as the client belong. The KvK puts it bluntly: there is a good chance that an unsecured creditor will get nothing or only a part. Many bankruptcies of small building firms even end "for lack of assets", with no payout at all. So plan your restart as if this money is gone; any payout often only comes after years and is then a bonus. If the business was a sole proprietorship or a general partnership (vof), the business owner is personally liable, but even then you share in the same order of priority.

Step 4: who owns the materials on the building site?

Three situations get mixed up here, and the answer differs for each one.

  • Incorporated into the home. Window frames that have been fitted, brickwork that is standing, pipes that have been laid: whatever has been permanently joined to your home has become your property by accession (Article 5:20 in conjunction with 3:4 BW). That also applies if the contractor never paid their supplier. The supplier can no longer take those items back; they only have a claim against the estate.
  • Delivered, not yet installed, paid for by you. If the packs of insulation or the bathroom were invoiced in your name and paid for, or if you agreed in writing with the contractor that paid materials are your property, then they belong to you. Present this to the curator with invoices and photos and do not let them be taken away.
  • Delivered, not yet installed, not paid for by you. This is the tricky case. Many building suppliers deliver under retention of title (Article 3:92 BW): they remain the owner until the contractor has paid. They can reclaim those materials through the curator. If there is no retention of title, the materials belong to the estate and the curator decides what happens to them. You may not simply start using them; ask the curator in writing whether you can take them over, often for a reasonable fee.

What you do in every case: take photos of everything that is lying there, secure the building site and don't let anyone collect anything without consulting the curator. If a supplier comes to remove materials without permission, refer them to the curator.

Step 5: subcontractors and suppliers knocking on your door

The plasterer, the installer or the timber merchant who were engaged by your contractor and have not been paid sometimes turn up at your door asking you to settle their invoices, sometimes suggesting that otherwise they will come and remove "their work". Legally it is simple: you have no contract with them. They have a claim against the bankrupt contractor and must submit it to the curator; you owe them nothing. If you pay them out of goodwill, you pay twice for the same work. What you can do: hire a subcontractor who knows the job directly for the remaining work, under a new, written contract and at a new price. In that case, agree explicitly that old claims against the contractor are excluded from that arrangement.

Step 6: quality-mark guarantee, insurance and legal expenses cover

Whether someone else bears the loss depends on what you arranged before the start. With a contractor affiliated with BouwGarant, you could take out a Verbouwgarantie (renovation guarantee) before the work began; in the event of bankruptcy it reimburses the extra costs of completion and after handover it covers hidden defects. The scheme must be taken out before the start, and requires a signed contract with a cost breakdown and a payment schedule in line with BouwGarant's rules; you receive a certificate as proof. If you have that certificate, report the loss immediately. The guarantee certificates of Woningborg and SWK (Dutch new-build guarantee institutions) are intended for buyers of a new-build home: they cover completion if the builder goes bankrupt and warranty complaints after handover, but they do not apply to an ordinary renovation of an existing home, unless your project has been registered under a specific renovation scheme of such a guarantee fund. Exactly what each quality mark covers is explained in Quality marks in construction explained.

A CAR insurance (contractors' all risks) covers physical damage to the works during construction, such as storm, theft or a burst pipe; the bankruptcy itself is not covered damage. If the CAR policy was taken out by the contractor, cover usually lapses with the bankruptcy and your half-finished renovation is left uninsured; inform your buildings insurer and ask whether your own CAR cover for the remaining period is possible. A legal expenses insurance with consumer or housing cover usually pays for legal help with writing to the curator, assessing the new contract and any disputes. If defects in the old work appear after handover, you can no longer recover them from the bankrupt contractor; how warranty works in that case is explained in Warranty after a renovation.

Step 7: carrying on with a new contractor

Before anyone else starts work, record the state of the work. Take detailed photos and video of every room, note what is finished, what is half finished and what is missing, and for a larger renovation have an independent building surveyor produce a condition report. That report is your evidence towards the curator (for your claim), towards the new contractor (to define the scope of their work) and later in case of defects. Ask the curator in writing to confirm that you may release the building site to a third party.

Then ask at least two contractors for a quote based on the condition report and the original drawings. A new contractor usually charges a surcharge for taking over half-finished work: they have to check what their predecessor did and sometimes redo parts. Record in the new contract which work is existing and which is new. Since the Wet kwaliteitsborging voor het bouwen (Wkb, the Dutch Quality Assurance for Construction Act), this is especially important: after handover the contractor is liable for defects that were not discovered at handover, unless those cannot be attributed to them (Article 7:758(4) BW). They will reasonably not want to bear that liability for the work of their bankrupt predecessor, so expect an exclusion for existing work and a separate handover of the new part. If your project falls under quality assurance, also inform the quality assurer and the municipality about the change of contractor. If you are financing with a construction deposit (bouwdepot), report the situation to the bank; some lenders ask for an amended renovation specification.

Preventing it on your next renovation

  • Pay according to progress. A limited first instalment, interim instalments at recognisable milestones and a final instalment after handover; after every payment, more work should be in place than you have paid for. What that looks like is explained in Deposits to the contractor.
  • Large sums only via a deposit account or guarantee. A notary's escrow deposit or a bank guarantee from the contractor keeps your money outside the estate.
  • Materials in your name. Have made-to-measure items with long delivery times invoiced in your name, or record in writing that paid materials are your property.
  • Check in advance. Look the company up in the Handelsregister (does it exist, who is the director, how long has it been around) and in the Centraal Insolventieregister; a previous bankruptcy of the same director is a warning sign, not a verdict.
  • Choose a quality mark with a completion guarantee and actually take out that guarantee before the start; membership alone covers nothing.
  • Watch for signals during the work. Suppliers who stop delivering, staff who disappear, requests to pay instalments early: in that case, hold back payment until the work is visible and ask for an explanation.

A bankruptcy also hits the tradespeople who worked for the contractor. The carpenter or bricklayer who knows your project is often the quickest route to a finished renovation, provided you make the arrangements again and in writing.

Frequently asked questions

Do I still have to pay a bankrupt contractor?
No, not the contractor directly. After the bankruptcy judgment, only the curator has authority over the contractor’s assets. Only pay outstanding instalments on the written instruction of the curator and only for work that has actually been carried out. A payment into the old account may not discharge your debt.
Will I get my deposit back if the contractor goes bankrupt?
Usually not, or only in part. Your claim for work not carried out is an unsecured claim that you submit to the curator with supporting evidence. The costs of the estate and preferential creditors such as the Belastingdienst (Tax and Customs Administration) come first. Many bankruptcies of small building firms end with no payout to ordinary creditors.
May I use the materials lying on the building site?
Materials already incorporated into the home have become your property by accession. Loose materials that you paid for yourself and that are in your name also belong to you. Loose materials that the contractor did not pay for may be subject to the supplier’s retention of title or belong to the estate; ask the curator in writing for a position before you use them.
Do I have to pay the bankrupt contractor’s subcontractors?
No. Subcontractors and suppliers have a contract with the contractor, not with you; they must submit their claim to the curator. You can, however, hire them directly for the remaining work, under a new written contract that explicitly excludes old claims.
Does a quality mark or insurance cover the costs of a bankruptcy?
Only if you took out a completion guarantee in advance, such as the BouwGarant Verbouwgarantie with an affiliated contractor; it reimburses the extra completion costs. Woningborg and SWK apply to new builds. A CAR insurance covers damage to the works, not the bankruptcy. A legal expenses insurance usually pays for the legal help.

Related articles

Regulations

Paying a deposit to your contractor: what is normal and how do you pay safely in instalments?

"Thirty per cent on signing, before Monday please": many renovations start with a request for a deposit. It is not compulsory. What the law does and does not say, which instalment arrangement is common in the industry, why the 5% rule only applies to new builds, how a deposit with a notary or a bank guarantee works, what an invoice must contain and which signs suggest you had better not pay in advance.

Read more
Advice

Quality marks in construction explained: BouwGarant, Woningborg, SWK, Techniek Nederland, KOMO, VCA, Erkend Installateur

Logos on the van, the website and the quote: BouwGarant, Woningborg, SWK, Techniek Nederland, KOMO, VCA, Erkend Installateur. But who awards such a quality mark, what has been assessed and what concrete use is it to you if something goes wrong? For each quality mark you can read what it gives you, what it specifically does not say and how to check in a register whether a company is genuinely entitled to use it, including the statutory CO certification for gas work.

Read more
Regulations

Guarantees after a renovation: how long, on what and from whom?

A leaking roof two years after handover, a tiled floor coming loose, a central heating boiler giving up: who pays? The law gives you more protection than most guarantee certificates, but it does have time limits and rules. What the Dutch Civil Code provides, what a contractual guarantee and a manufacturer’s warranty add, which periods are common in the industry and what a guarantee scheme does if the contractor goes bankrupt.

Read more

More in Regulations

Regulations

Fitting a roof window: permit-free, leaks and what the carpenter does

More daylight and fresh air in the attic without a dormer: a roof window is often the simplest solution. Which type suits your roof, when is a roof window or rooflight permit-free, including at the front, what changes for a listed building or in a VvE (owners' association), how does the carpenter deal with rafters and purlins, why does a roof window leak and which VAT rate applies?

Read more
Regulations

Permit-free rear extension: the rules for the back garden

An extension at the back of the home is in many cases permit-free, but only if you stay within fixed dimensions: the depth from the original rear facade, the height and the percentage of the plot you may build on. Under the Omgevingswet, those dimensions are in the bruidsschat (the transitional national rules) of your municipality's omgevingsplan, alongside the technical building requirements of the Besluit bouwwerken leefomgeving. This article explains how the two tests work, which dimensions apply, what neighbour law says, which technical building requirements always remain and who to hire for the work.

Read more
Regulations

Felling a tree in your garden: when do you need a felling permit?

Whether you may fell a tree in your own garden is decided by your municipality: the rules are set out in the omgevingsplan (municipal environment plan) and differ from place to place, usually with a threshold for trunk girth and a list of protected trees. On top of that come the bird breeding season and the protection of animals, neighbour law on branches and distance from the boundary, and your duty of care as owner in the event of storm damage. When to apply for a permit, when pruning is enough and when to bring in a tree surgeon.

Read more

Need a tradesperson?

Find a qualified tradesperson near you. Post your job for free, or sign up on VerbouwPro as a tradesperson.